Introduction
Demolition is dealt with under the Building Act 1984. Generally, it requires six weeks prior notice to be given to the Local Authority Building Control before demolition begins.
The Local Authority Building Control may decide to issue a notice within six weeks on receipt of the notification to specify conditions that need to be met which may include precautions to protect adjoining properties and the public.
Demolition work must also comply with the Construction (Design and Management) Regulations 2007 and a health and safety plan produced by the principal contractor
Building Regulations relating to site preparation and resistance to contaminants and moisture will need to be met once the preparation work starts on the site.
What you need to submit
The list below details supporting documents that may need to be submitted as part of your application. Please refer to each section below in order to determine whether or not you need to submit it as part of your application.
Demolition notice application form
Always required
Apply using the form below.
The correct fee
No fee is required for this application.
Contact building control and dangerous structures
- Email: buildingcontrol@peterborough.gov.uk
- Telephone: 01733 453422 (between 9am-1pm)
- Out of hours: 01733 864157
- Write: Building Control, Sand Martin House, Bittern Way, Fletton Quays, Peterborough PE2 8TY